Thanks to European Union, financial resources are being drawn from European funds for motorway construction. Each construction has its own conditions and the amount of drawn finances.

Funding programmes
of European Union

Cohesion Fund
It is EU financial tool supporting expensive transport and environmental investment projects.
The aim of the fund is to reduce economical and social differences among
the EU countries by co-financing those projects.   
 
Structural fund (European Regional Development Fund)
It is a supporting tool of European Union which regional development projects are co-financed by.
The fund is intended to reduce economical and social differenced among regions.      
 
TEN-T programme
Financial resources of European Union supporting those projects
which help to establish trans-european networks in the field of transport, energy and telecommunications.

 

Financial help from European union in the field of transport is drawn according
to approved program document of the Slovak Republic for certain period.


2004 – 2006
Operational programme
Basic infrastructure

2007 – 2013
Operational programme
Transport

2014 – 2020
integrated regional
operational programMe 

List of projects
co-financed by
european union funds

2004 - 2006 Operational programme basic infrastructure

Cohesion Fund

Project Stage Financed EU Resources

D1 Mengusovce – Jánovce                                                                   

in operation construction works 140 910 025.10 €

Structural fund

Project Stage Financed EU resources
R1 Rudno nad Hronom – Žarnovica                                                    in operation construction 47 463 753,88 €
R2 Ožďany, bypass in operation construction 33 800 874.13 €
R2 Figa, bypass in operation construction 12 418 027.01 €
R4 Svidník, bypass in operation construction 11 552 079.16 €
Project preparation of section R1, R2, R4 in preparation project preparation 1 946 609.66 €

TEN-T programme

Project Stage Financed EU resources
D3 Svrčinovec – Skalité                                                                       in operation project preparation 5 194 019.92 €

2007 - 2013 Operational programme transport

Cohesion Fund

Project Stage Financed EU resources
D1 Dubná Skala – Turany                                                                               in operation construction works 66 337 322.10 €
D1 Jánovce – Jablonov in operation construction works 146 644 361.39 €
D1 Studenec – Beharovce in operation construction works 15 749 390.93 €
D1 Fričovce – Svinia in operation construction works 67 914 855.20 €
D3 Hričovské Podhradie – Žilina, Strážov in operation construction works 66 980 400.14 €
R4 Košice – Milhosť in operation construction works 42 743 406.36 €
D1 Hubová – Ivachnová in operation construction works 19 602 988.62 €
Project preparation of section D3 in preparation project preparation 4 466 617.07 €
R3 Horná Štubňa, bypass in operation construction works 7 867 906.60 €
D1 Hričovské Podhradie – Lietavská Lúčka in construction construction works 94 959 511.48 €
D1 Turany – Hubová in preparation project preparation 2 576 795.52 €
D3 Svrčinovec – Skalité in operation construction works 130 311 953.28 €
D1 Lietavská Lúčka – Višňové – Dubná Skala in construction construction works 16 927 872.17 €
D1 Nová Polhora, feeder in preparation construction works 5 218 962.64 €
D3 Žilina, Strážov – Žilina, Brodno in operation construction works 63 366 292.15 €
Increasing safety D1 Prešov – Budimír in operation construction works 9 271 703.61 €
D1 Prešov,west – Prešov, south in construction project preparation 5 490 589.64 €
Increasing safety R1 Trnava – Nitra in operation construction works 9 987 717.91 €
Increasing safety R1 Šášovské Podhradie – Zvolen in operation construction works 2 934 564.91 €
Project preparation of section:
D1 Bidovce – state border SK/UA 
D3 Žilina, Strážov – state border SK/PL 
R2 intersection D1 – Nováky 
R2 Kriváň – Tornaľa 
R2 Tornaľa – Včeláre 
R2 Včeláre – Košické Olšany 
R3 Šahy – Zvolen 
R4 state border SK/PL – Kapušany

 

 

 

in preparation

 

 

 

project preparation

 

 

 

1 422 592.95 €

D2 Moravský Svätý Ján, ecoduct in construction construction works 4 359 851.52 €
Intersection D1 Senec, stage 0 in operation construction works 1 643 689.19 €
Increasing safety D1 Ivachnová – Važec in operation construction works 7 948 112.69 €
Increasing safety D1 Trnava – Lúka in operation construction works 8 576 769.88 €
D1 Sverepec - Vrtižer in operation construction works 211 419 831.45 €

Structural fund

Project Stage Financed EU resources
R1 Žarnovica – Šášovské Podhradie                                                              in operation construction works 110 850 831.99 €
R2 Zvolen, east – Pstruša in operation project preparation 329 317.02 €
R2 Pstruša – Kriváň in operation project preparation 412 122.20 €
R4 Prešov, severný bypass in operation project preparation 2 845 445,33
R2 Žiar nad Hronom, bypass in operation construction works 21 585 660.83 €
R2 Ruskovce – Pravotice in operation construction works 55 863 848.73 €
R2 Zvolen, east – Pstruša in operation construction works 17 137 760.28 €
R2 Pstruša – Kriváň in operation construction works 125 868 221.73 €

Project preparation of section:


R2 Rožňava – Jablonov nad Turňou
R2 Šaca – Košické Olšany

 

 

in preparation

 

 

project preparation

 

 

667 676.62 €

TEN-T programme

Project Stage Financed EU resources
D1 Budimír – Bidovce                                                                           in operation project preparation 1 491 176.72 €

2014 - 2020 Integrated regional operational programme 

Cohesion Fund

Project Stage Financed EU resources
D1 Hričovské Podhradie – Lietavská Lúčka, II. phase                                  in operation construction works 231 637 303.00 €
D1 Budimír - Bidovce in operation construction works 143 667 620.00 €
D1 Lietavská Lúčka - Višňové - Dubná Skala, II. phase in construction construction works 273 301 668.08 €
D1 Prešov západ - Prešov juh in construction construction works 278 317 478.82 €
D3 Čadca Bukov - Svrčinovec in construction construction works 71 644 484.07 €
D3 Žilina, Strážov – Žilina, Brodno, II. phase in operation construction works 124 236 548.00 €
D3 Svrčinovec – Skalité, II. phase in operation construction works 112 115 000.00 €

 

Structural fund

Project Stage Financed EU resources
R2 Zvolen, východ – Pstruša, II. phase                                                             in operation construction works 37 460 010.44 €

CEF

Project Stage Financed EU resources
D3 Čadca, Bukov - Svrčinovec                                                                            in construction construction works 74 317 452.08 €